Wiring in a PLC Control Panel

 In this article, you will learn the wiring in a PLC control panel and the basic electrical design of a PLC system cabinet.

Wiring in a PLC control panel is a hectic job and requires a good understanding of PLC standards as well as electrical standards.

Basically, before PLC was being started to be used in the market, wiring was the only method to provide control of a system.

Wiring interlocks need a good understanding of the logic to be implemented as well as the electrical standards that need to be implemented to fulfill it. So, it is said the one who is a master in designing and understanding electrical wiring logic and interlock can easily write a PLC logic too.

In this post, we will see how to design a PLC system cabinet. In simpler terms, consider that you are wiring an electrical PLC panel.

Wiring in PLC

Refer to the below image. We will consider a simple panel here, with all the basic electrical components.

The PLC panel consists of the main breaker switch, bus bar, circuit breakers, relays, contactors, PLC, fuses, SMPS, terminal boards, utility sockets, and earthing points.


Main Breaker Switch

Let us start with the main breaker switch. This is the point where the main power supply (3 phases) is connected (R, Y, B, N). It is this point that supplies power to all the components.

Install the breaker in such a way that the wireman gets a free hand to do the wiring; because any lag in it can damage the whole system.

Busbar

In the next step, connect the output of the main breaker switch to the busbar. The bus bar provides proper electrical distribution.


So, if there are many components in the panel which requires a single-phase supply or three-phase supply, then the bus bar is the most efficient step to do it.


Distribute all the points from here to the ones which require single phase or three phase supply. This will help you in easy and efficient power management.


You cannot just loop the three-phase wires to different components, as it is a wrong practice and can damage the wiring or the whole electrical panel in totality.


Circuit Breakers

Now, suppose there are three circuit breakers in the panel. Connect the three phase wires from the bus bar to each of the circuit breaker inputs.

Individual circuit breakers will power individual contactors connected to their output. This will give proper output control to the contactors.


Because contactors have a control circuit that is controlled by the PLC; thus giving individual three-phase control too will give proper electrical control over the final output.


SMPS

Now, from the bus bar, connect one point to the SMPS. This will power it up and give DC output to the cabinet.


If the current rating of SMPS is higher, then you can use a distribution terminal board too for DC supply. This will properly segregate the DC supply to all the components requiring it. From this, power the PLC.

Now, after this, we will see how to wire the PLC IOs.


Digital Inputs

Firstly, take digital inputs. According to sink or source wiring, connect either 24V or 0V to the PLC common.


So, for example, if the common is 24V, connect 0V to all the respective PLC field inputs in the terminal board.


As one board has two pins, one will be used to provide 0V and the other will be connected to PLC digital input.

For safety, many use fuse terminal boards. This provides additional safety to the field devices.


Digital Outputs

Then, coming to digital outputs, the same sink and source theory applies to it.


So, for example, if the common is 24V, connect 0V and PLC digital outputs to all the relays (relay has two pins, so one pin will be 0V and the other pin will be PLC digital output).


According to the output you want at relay output (DC or AC), connect the wiring accordingly.

For example, if the relay output required is 230V AC, connect the line wire to the common and connect the NO wire to the contactor’s line input. Connect the neutral wire to the contactor’s neutral input and thus, the circuit is complete.


Now, whenever the relay turns on, that particular contactor will turn on and if its MCB is on, then the three-phase supply will be passed on to the final output.


Analog Inputs and Outputs

Now, analog input and analog outputs will be directly routed through terminal boards with respect to PLC.


If possible, use fused terminal boards for additional safety.

Terminal Boards

Coming back to the contactors, the output is connected to terminal boards where you can connect your final output.

Note down some general points while designing a PLC panel:

  1. Have a good understanding of electrical ratings and standards, before choosing a component; for example, a contactor.
  2. Many times, fuses are connected after the mains breaker switch to protect the panel from any damage caused by the incoming three-phase supply. Also, transformers are used in many panels to step down a voltage according to the requirements.
  3. Fuses are also installed after SMPS for protecting PLC or other sensitive field devices.
  4. If three phase devices are used with earth points, ensure to provide separate earthing (power and instrument) in the panel. Do not mix them up.
  5. In this example, I have not shown terminal boards for PLC digital outputs; but even they are used normally in many applications. Because there can be valves in the system which require 24V DC, and such outputs require terminal wiring in the boards.

Many types of designs are possible in a PLC cabinet. You should know the basic requirements and have a fair idea of electrical wiring and PLC wiring, which will help in designing the panel properly.

Comments

Popular posts from this blog

PLC Program for Mixing Tank

 Create a ladder diagram for controlling a batch mixing process. Implement a PLC program for mixing tank or Mixing Process using PLC Ladder Logic. PLC Program for Mixing Tank Fig : Mixing tank A tank is used to mix two liquids. The required control circuit operates as follows: A. When the START button is pressed, solenoids A and B energize. This permits the two liquids to begin filling the tank. B. When the tank is filled, the float switch trips. This de-energizes solenoids A and B and starts the motor used to mix the liquids together. C. The motor is permitted to run for 1 minute. After 1 minute has elapsed, the motor turns off and solenoid C energizes to drain the tank. D. When the tank is empty, the float switch de- energizes solenoid C. E. A STOP button can be used to stop the process at any point. F. If the motor becomes overloaded, the action of the entire circuit will stop. G. Once the circuit has been energized, it will continue to operate until it is manually stopped. Solution : A

What is Relay? How it Works? Types, Applications, Testing

 We use relays for a wide range of applications such as home automation, cars and bikes (automobiles), industrial applications, DIY Projects, test and measurement equipment, and many more. But what is Relay? How a Relay Works? What are the Applications of Relays? Let us explore more about relays in this guide. What is a Relay? A Relay is a simple electromechanical switch. While we use normal switches to close or open a circuit manually, a Relay is also a switch that connects or disconnects two circuits. But instead of a manual operation, a relay uses an electrical signal to control an electromagnet, which in turn connects or disconnects another circuit. Relays can be of different types like electromechanical, solid state. Electromechanical relays are frequently used. Let us see the internal parts of this relay before knowing about it working. Although many different types of relay were present, their working is same. Every electromechanical relay consists of an consists of an Electroma

Chlorine dioxide Analyzer Principle

 Chlorine dioxide measurement Chlorine dioxide (ClO2) is an instable, non-storable, toxic gas with a characteristic scent. The molecule consists of one chlorine atom and two oxygen atoms – represented in the chemical formula ClO2. It is very reactive. To avoid the risk of spontaneous explosions of gaseous chlorine dioxide or concentrated solutions, it is generally handled in dilution with low concentrations. ClO2 is soluble in water, but tends to evaporate quickly. Typically it is prepared on site, for example from hydrochloric acid and sodium chlorite. The procedure provides solutions with approx. 2 g/l ClO2 that can be safely handled and stored for several days. Image Credits : krohne Sensor Parts : Reference electrode Applied chlorine dioxide specific potential Current needed to maintain the constant potential Counter electrode Measuring electrode The disinfection effect of ClO2 is due to the transfer of oxygen instead of chlorine, so that no chlorinated byproducts are formed. ClO2