PLC or DCS Control System Spares

 In general, spares in the control system (PLC or DCS) are defined as consumable spares, commissioning spares, installed spares, 2 years operational spares, and mandatory spares.


Control System Spares

Consumable spares and commissioning spares
Consumable spares and commissioning spares are normally recommended by the system vendor supplier.

These spares are meant to be consumed before the system is fully operational and these are required to avoid using any of the recommended operational spares. These spares are ordered along with main items.

For instance, Fuses, terminals, relays, printer cartridges, A3/A4 papers, and so on.

Installed spares
Installed spares as the name indicate, are installed within the control system. These spares are utilized when there is the failure of a component within the system so by using installed spare; the system is operational without any downtime.

The requirement of installed spare shall be defined as part of the project scope. Assume if one channel from 16 channel I/O card is not working then it is reconfigured with an installed spare within that I/O module.

Wired spares (as part of installed spare) are a ready-to-operate condition when field cable is connected to spare assigned terminals. Installed spares serve the purpose of replacement and/or future expansion/modification of the system.

Therefore, it has a significant role in overall control system design and its capacity.

2 Years Operational Spares
2 Years operational spares are essential for the continual operation of the control system. This set of spare includes small items (fuses, relays) to large items (Controllers, servers). The scope of supply of these spares depends upon the project scope.

However, a list of recommendations can be provided by the control system vendor. These spare parts are in form of loose supply and not installed into the system.

On contrary, few spares take longer delivery time, hence, it is beneficial to have them in the warehouse to ensure the continual operation of the plant.

Mandatory Spares
Once in a while, the mandatory spares are described as a part of the project scope. These are also loose spares like 2 Years operational spares and can be used in a lieu of 2 years operational spares.

These spares are used for the substitution of failed components or can also be used for future expansion.

Predominantly, spare space is also considered within the control system to ensure future capacity expansion.

Spare Requirement
It is paramount to understand the spare requirement defined in projects.
  • 20% installed, wired, and fully functional I/O for all types(including Field Termination Arrays or equivalent)
  • Spares in I/O modules are not necessarily identical as spares required in mutlipair/ or multi core cable.
  • Spare pairs of the incoming cables should be terminated on spare terminals in the marshalling cabinets.
  • Since I/O Module is specified as wired, it means that wiring up to I/O module is also needed along with associated accessories.
  • These spares are required for each type of I/O channels; these shall be fully wired from the terminal block, relay, fuses, barriers, etc. This is a paradigm of installed spare.
  • For instance, if you have analog input as 2 wire, 3 wire, 4 wire, analog interface with MCC, IS type, Non IS type then you should have all these I/O as spare for each type. Analog input channels with different I/O adaptor should also be considered as different I/O type.
  • Also, this spare should be dedicated to each type of system (e.g. DCS, ESD, and F&G). Each system should have evenly distributed spare I/Os. It is worthless to provide 30% Spares in DCS and 10% spares in ESD and 20% in the F&G system.
  • These spares are required as cumulative, not as per individual location/cabinet wise. Suppose your control system is spread over various locations within the plant (Remote I/O panels), then in each location, you may not need to meet 20%. However, as a total, you should meet the requirement.
  • Since installed spare I/Os are wired up to I/O modules, processor loading should be inclusive of installed spares then processor spare capacity should be calculated. This is grey area for many. Hence, this shall be mutually agreed upon.
  • Spare Space in the cabinet: Minimum 20% free space.
  • 20% spare capacity in trunk/duct after cabling and wiring has been installed
  • Even if the installed spares are installed within the cabinet, 20% free space is also necessitated to install components like I/O modules, Terminals, barriers, or even controllers for future capacity expansion. Hence, the associated cable duct should also have some spare space for wiring.
Spares Calculation
Additional examples of installed spares are as follows

  • Cable gland plate: 20% spare space in cable gland plate of the cabinet
  • Fibre Optic: 100% spare fibers in fiber optic cable
  • Power supply: 25% spare capacity after completion of SAT
  • System memory (RAM): 50% spare capacity in each workstation/server
  • Storage capacity: 50% spare capacity in each workstation/server after completion of SAT
  • Software license: 50% spare capacity in each workstation/server
  • Controller /processor loading: 40% spare capacity after completion of SAT
  • Network loading: 40% spare capacity after completion of SAT
Understanding of Spare Parts and Spare Space
Sometimes, it is pivotal to have a clear mutual understanding of spare parts and spare space when there are ambiguous requirements specified.

  • Location-wise or cabinet wise spare I/Os or terminals requirement.
  • When you have universal or configurable I/O types then spare I/O types requirement can be optimized and overall spare requirement can be mutually agreed upon as part of the contract.
  • Spare space should be altogether considered in each type of cabinet. It has no meaning to provide one spare cabinet and fully load the other cabinets.
  • It is essential to consider spare accessories like a relay, barriers/isolators, adaptors, fuse along with each type of I/Os especially when spare accessories are not specified in the project specification.
It is more appropriate to ask in case of unclear requirements as it will have an impact on overall control system design and related deliverables such as
  • I/O assignment,
  • Cabinet GA Diagram,
  • Bill of Materials, etc.



Comments

Popular posts from this blog

PLC Program for Mixing Tank

 Create a ladder diagram for controlling a batch mixing process. Implement a PLC program for mixing tank or Mixing Process using PLC Ladder Logic. PLC Program for Mixing Tank Fig : Mixing tank A tank is used to mix two liquids. The required control circuit operates as follows: A. When the START button is pressed, solenoids A and B energize. This permits the two liquids to begin filling the tank. B. When the tank is filled, the float switch trips. This de-energizes solenoids A and B and starts the motor used to mix the liquids together. C. The motor is permitted to run for 1 minute. After 1 minute has elapsed, the motor turns off and solenoid C energizes to drain the tank. D. When the tank is empty, the float switch de- energizes solenoid C. E. A STOP button can be used to stop the process at any point. F. If the motor becomes overloaded, the action of the entire circuit will stop. G. Once the circuit has been energized, it will continue to operate until it is manually stopped. Solution...

What is Relay? How it Works? Types, Applications, Testing

 We use relays for a wide range of applications such as home automation, cars and bikes (automobiles), industrial applications, DIY Projects, test and measurement equipment, and many more. But what is Relay? How a Relay Works? What are the Applications of Relays? Let us explore more about relays in this guide. What is a Relay? A Relay is a simple electromechanical switch. While we use normal switches to close or open a circuit manually, a Relay is also a switch that connects or disconnects two circuits. But instead of a manual operation, a relay uses an electrical signal to control an electromagnet, which in turn connects or disconnects another circuit. Relays can be of different types like electromechanical, solid state. Electromechanical relays are frequently used. Let us see the internal parts of this relay before knowing about it working. Although many different types of relay were present, their working is same. Every electromechanical relay consists of an consists of an Elect...

Chlorine dioxide Analyzer Principle

 Chlorine dioxide measurement Chlorine dioxide (ClO2) is an instable, non-storable, toxic gas with a characteristic scent. The molecule consists of one chlorine atom and two oxygen atoms – represented in the chemical formula ClO2. It is very reactive. To avoid the risk of spontaneous explosions of gaseous chlorine dioxide or concentrated solutions, it is generally handled in dilution with low concentrations. ClO2 is soluble in water, but tends to evaporate quickly. Typically it is prepared on site, for example from hydrochloric acid and sodium chlorite. The procedure provides solutions with approx. 2 g/l ClO2 that can be safely handled and stored for several days. Image Credits : krohne Sensor Parts : Reference electrode Applied chlorine dioxide specific potential Current needed to maintain the constant potential Counter electrode Measuring electrode The disinfection effect of ClO2 is due to the transfer of oxygen instead of chlorine, so that no chlorinated byproducts are formed. C...