DCS Commissioning Steps

 

Physical Checks

  • All civil works required for DCS cabinet installation shall be completed.
  • Ensure painting work is completed in the area.
  • Ensure completion of false flooring in the area, if applicable
  • Ensure proper lighting available in the control room and Panel Room.
  • Ensure HVAC is commissioned for the area or ensure proper ventilation in the area.
  • Ensure proper installation and fixing of the panels at the location as per GA drawing.
  • Check and ensure anti-vibration pads of the panels are in place.
  • Check that dust filter on louvers is clean, for indoor panels
  • Check DCS panels for the physical damage – Door lock, door limit switch, Fans, Tube lights, internal cables, MCBs, isolators, modules, racks, controllers, prefab cables, etc.
  • Check all the components of the panel as per BOM. Check for loose supplied items.
  • Check and verify all hardware like Engineering and operator station as per BOM.

Pre-Requisites

  • Ensure availability of approved DCS GA drawings, System Architecture Drawing, Network interconnection, Power wiring and distribution, Earthing wiring drawings, Functional design Specification for DCS, I/O list/nest loading, Instrument list, Bill of Material, Cable termination schedule, P&ID Drawings, Control narrative/process description, logic diagram, FAT Reports, etc.
  • Ensure availability of instrumentation technicians, engineers, programmers, and tools – like Screw Driver, Tester, Digital Multimeter, Insulation resistance tester, Earth pit resistance checker, 4-20 mA source, HART communicator, Loop check tester, short links, etc.
  • Ensure UPS (redundant) and Non-UPS (Utility) power supply is available. Before charging the DCS check whether UPS and battery banks commissioning is completed.
  • Operator work Station (OWS), Engineering work station (EWS) HMI are ready with installed software as per system requirement.  Check Antivirus is installed.
  • Ensure the Latest backup of FAT logic, Graphics configuration available.
  •  Check the validity of license software for HMI and Logic software/configuration software.
  •  Electronic/instrument (IE) and Intrinsically Safe (IS) earth pit/grid is ready as per installation drawing. Cabling from earth pit or IS Earth Grid to DCS Panel is completed. Isolation between instrument Earth and panel earth/ cabinet body earth/system earth (SE).
  • Master clock signal is available
  • Test schedule, agenda, roles and responsibility matrix should be available.

Safety

  • The area under commissioning shall be tagged and PTW (Permit to Work) is issued/available.
  • To protect personnel and the equipment in the area of commissioning, “area restrictions” shall be displayed/tagged.
  • Use of PPE is mandatory

Brief DCS Commissioning Steps

Below is a general guideline to have an overview of commissioning steps.

One has to follow agreed templates/checklists/procedures or protocols for the entire DCS system commissioning.

Cabinet and console furniture hardware check

Make, model, color, thickness, dimensions, component mounting, safety sticker.

Verification of component inside the cabinet/console and its specification w.r.t approved documents.

Labeling check 

It is to verify that the cabinet nameplates and component labels.

All components inside the cabinet (Controllers, firewalls, switches, I/O modules, barriers/isolators, racks/nodes, Power supply modules, terminals & its size, relay boards, Safety earth, instrument earth, MCBs, MCB rating, sockets, cross ferrule, patch panels, convertors, servers,  etc) shall be properly labeled so that can be easily identified.

The workmanship is verified.

Internal Wiring check

It is to verify that the cabinet internal wirings are as per the project specification and approved drawings.

AC power, DC power, signals (AI, AO, DI, DO, RTD, TC, Special modules) internal wiring, earthing wire color, size, duct color.

Continuity check.

MCBs / isolators check.

Fuse rating check.

Cable dressing check.

Main cable installation, termination, gland plates, and sealing shall be verified.

Nest loading and I/O assignment check

It is to verify controllers, racks, slots, modules, etc

System startup check

This includes UPS and non-UPS Power check, Earthing check.

When required parameters are within tolerance then power on of system is done step by step.

Ensure that all components automatically boot up and components are in healthy condition.

Cabinet Alarm Check

It is to verify the cabinet alarm functionality when a hardware failure occurs.

Verification of temperature switch, fan modules, Power supply modules, etc.

This should be used for cabinet diagnosis purpose.

Redundancy Check

It is to verify that system operation is uninterrupted when the active hardware fails.

This test is conducted for

  • redundant power supply (bulk and system power supply),
  • redundant controllers/ CPU,
  • Redundant communication buses(I/O modules to nodes/racks,
  • nodes to controllers,
  • controllers to switches,
  • switches to stations,
  • redundant I/O modules,
  • redundant servers,
  • GPS systems, etc

System Architecture Check

It is to verify that all components are completely networked.

Interconnection of components to be verified.

Ensure that all IP addresses are properly configured uniquely for each station including printers.

Time Synchronization Check

It is to verify time matches & synchronizes with the GPS time.

This includes visual checking of

  • GPS antennas,
  • GPS receivers,
  • NTP/SNTP switches, and their power on.

GPS time shall appear in all synchronized stations.

Software License Check

It is to check all applicable licenses for Workstation (Operator, engineering) and its applications like a logic builder, HMI, reports, server licenses, etc.

This shall be documented as part of BOM and verified in each station.

Graphic Check

Graphics layouts checking w.r.t P&ID, shape, size, backgrounds, and icon color when status changes (red, green, blue, etc).

Faceplate, tagging, the description shall be checked.

Functionally as per the requirement of the process (Auto, manual, local, remote, bypass, etc) shall be implemented.

Few activities can be done in parallel to I/O loop checking.

I/O Loop check

I/O Assignment is configured properly in PCS. Marshalling wiring and termination matches with I/O allocation.

This can be done either cold loop or hot loop testing. Cold loop checking means loop checking is done without powering on instruments.

Only wiring continuity is checked from field to Junction Box and then to the control room. Hot loop checking is done by powering the instrument.

At the site, it is good to perform a cold loop check first and then perform a hot loop check with actual instruments and interfaces.

All the I/Os connected to the system is checked.

Logic Check

It is to verify Control Algorithm Implementation with reference to logic diagrams, functional schematics, or control narrative.

Nest loading is also important to know associated I/O tags and their addresses.

Alarm and trip value to be verified. Closed-loop control (PID parameters) and controller action to be verified.

Logical opening/closing of valves/dampers, starting or stopping of drives (pumps, compressors, etc) to be verified.

All interlocks, start permissive and first-out logics are tested.

Trend & Control Group, Log Reports

It is to verify Trend Input, Historical message, Alarm summary, SOE.

Trend group is necessary during logic/ loop testing and plant operation to know the accurate functioning of relevant inputs and outputs.

Log reports are necessary to know the overall inputs, outputs, and performance of the plant and to plan the resources and future maintenance. Along with this, printer functionality is also tested.

Controller Loading Check

It is to verify Controller loading shall not be more than 60 %.

As some spare capacity is required for future expansion or modification.

Online / Offline Program Loading

It is to verify system behavior Online or offline Configuration/Modification from the engineering station.

System vendors detailed procedure shall be followed while doing so.

Scan Time Check

It is to demonstrate that controller’s actual scan time is within the project specification. This is more relevant to the safety system.

However, this can also be performed for DCS.

Login Users and their access

It is to verify what type of access the operator/engineer or manager has.

Communication with 3rd party systems

It is to verify system communication with third party systems.

Usually, this communication will be Modbus RTU (RS 485), Modbus TCP/IP, OPC, and IEC 61850 for electrical systems.

Configurations, software, and hardware are verified.

Graphics and logics testing is done.

Modification

Change management procedures to be followed and documented.

Spare Check

It is to verify the installed spares within the system, commissioning spares, operational spares as per contract requirement.

Sometimes this also includes Spare space checking inside the cabinet, Hard drive space, etc.

Miscellaneous Checks

depending upon project scope of work other functionality of hardware or software can be checked like

  • Asset management,
  • cybersecurity,
  • alarm rationalization,
  • Partial stroke testing,
  • HART multiplexer (master and slaves), etc

Punch list

It is to document all non-conformances or faults found on the system during the acceptance test along with their corrective actions.

At the site, one can have an overview of open punch points during the FAT test at vendor works. These non-conformances can be attended as per the agreed schedule and resources.

Reports

once all the tests are completed, all the relevant test reports shall be preserved and handed over to end-user.

All the changes in affected drawings, documents, configuration shall be properly marked for As-built documentation.

Handover

once all the non-conformances are clear, a certain performance period is over, DCS can be handed over to the end-user.

It is essential to have proper training in the DCS system before working on the same.



Comments

Popular posts from this blog

PLC Program for Mixing Tank

 Create a ladder diagram for controlling a batch mixing process. Implement a PLC program for mixing tank or Mixing Process using PLC Ladder Logic. PLC Program for Mixing Tank Fig : Mixing tank A tank is used to mix two liquids. The required control circuit operates as follows: A. When the START button is pressed, solenoids A and B energize. This permits the two liquids to begin filling the tank. B. When the tank is filled, the float switch trips. This de-energizes solenoids A and B and starts the motor used to mix the liquids together. C. The motor is permitted to run for 1 minute. After 1 minute has elapsed, the motor turns off and solenoid C energizes to drain the tank. D. When the tank is empty, the float switch de- energizes solenoid C. E. A STOP button can be used to stop the process at any point. F. If the motor becomes overloaded, the action of the entire circuit will stop. G. Once the circuit has been energized, it will continue to operate until it is manually stopped. Solution...

What is Relay? How it Works? Types, Applications, Testing

 We use relays for a wide range of applications such as home automation, cars and bikes (automobiles), industrial applications, DIY Projects, test and measurement equipment, and many more. But what is Relay? How a Relay Works? What are the Applications of Relays? Let us explore more about relays in this guide. What is a Relay? A Relay is a simple electromechanical switch. While we use normal switches to close or open a circuit manually, a Relay is also a switch that connects or disconnects two circuits. But instead of a manual operation, a relay uses an electrical signal to control an electromagnet, which in turn connects or disconnects another circuit. Relays can be of different types like electromechanical, solid state. Electromechanical relays are frequently used. Let us see the internal parts of this relay before knowing about it working. Although many different types of relay were present, their working is same. Every electromechanical relay consists of an consists of an Elect...

Chlorine dioxide Analyzer Principle

 Chlorine dioxide measurement Chlorine dioxide (ClO2) is an instable, non-storable, toxic gas with a characteristic scent. The molecule consists of one chlorine atom and two oxygen atoms – represented in the chemical formula ClO2. It is very reactive. To avoid the risk of spontaneous explosions of gaseous chlorine dioxide or concentrated solutions, it is generally handled in dilution with low concentrations. ClO2 is soluble in water, but tends to evaporate quickly. Typically it is prepared on site, for example from hydrochloric acid and sodium chlorite. The procedure provides solutions with approx. 2 g/l ClO2 that can be safely handled and stored for several days. Image Credits : krohne Sensor Parts : Reference electrode Applied chlorine dioxide specific potential Current needed to maintain the constant potential Counter electrode Measuring electrode The disinfection effect of ClO2 is due to the transfer of oxygen instead of chlorine, so that no chlorinated byproducts are formed. C...